Work begun | 1999 |
Opened | June 2003 |
Technical | |
Design engineer | Sadrul Ola Rizvi (Project Director - Indus Highway NHA) |
Length | 1.89 km (1+1⁄8 mi) |
Tunnel clearance | 3 m (9 ft 10 in) |
Width | 10.3 m (33 ft 10 in) |
The Kohat Tunnel (Urdu: کوہاٹ سرنگ, Kohat Surang) is a 1.9-kilometre-long (1+1⁄8-mile) highway tunnel under the Khigana Mountains between Kohat District and Dara Adam Khel Tehsil in the Khyber Pakhtunkhwa province of Pakistan. The tunnel carries northbound and southbound traffic along N-55 National Highway (Indus Highway) under the Kohat Pass. The tunnel is also referred to as the Pak-Japan Friendship Tunnel, as the tunnel was constructed in assistance with the Economic Cooperation Fund of Japan.[1]
History
![](http://upload.wikimedia.org/wikipedia/commons/thumb/f/fb/Kohat_Tunnel.jpg/220px-Kohat_Tunnel.jpg)
Construction on the tunnel began in 1999, and opened to traffic in June 2003. As part of the developing Indus Highway system, the tunnel serves as a shorter, alternate route to the Kohat Pass, situated between the cities of Peshawar and Kohat. The new route decreases the time required to travel through the Kotal Pass by about 20 minutes. The main advantage of the tunnel is that long bodied vehicles can now use the Indus Highway whereas previously the hairpin bends on the Kotal Pass made it impossible for such vehicles to travel. It also helps alleviate traffic congestion, improve traffic safety and promote economic development.
The tunnel was at the center of a military confrontation between the Pakistan Army and pro-Taliban militants in early 2008. The militants had taken control of the tunnel around 24 January, after hijacking trucks carrying supplies and ammunition for security forces in South Waziristan. On 27 January, Pakistan Army brought the tunnel back under control of the security forces, after "fierce fighting" involving artillery, helicopter gunships and heavy machine guns during which 24 militants were reported to have been killed.[2][3]
Features and specifications
- Total project cost: Rs. 662.6 million (US$2.3 million)
- Length of north section: 7.7 kilometres
- Length of south section: 22.20 kilometres
- Black topped: 7.3 metres
- Shoulders: 3.0 metres
References
- ^ "Construction of Kohat tunnel". www.pakistaneconomist.com.
- ^ Pak army kills 25 pro-taliban militants, recaptures tunnel-Pakistan-World-The Times of India
- ^ "AFP: Pakistan troops pound militants holding key tunnel: officials". Archived from the original on 20 May 2011. Retrieved 27 January 2008.
- Pages using gadget WikiMiniAtlas
- Articles with short description
- Short description is different from Wikidata
- Use dmy dates from June 2023
- Use Pakistani English from June 2023
- All Wikipedia articles written in Pakistani English
- Coordinates on Wikidata
- Articles containing Urdu-language text
- Wars involving the Taliban
- Tunnels completed in 2003
- Japan–Pakistan relations
- Road tunnels in Pakistan
- Tunnels in Pakistan
- All stub articles
- Pakistan geography stubs
- Pakistan transport stubs