StatusCommissioned
Construction began2019
Commission date2020
Operator(s)Ridi Hydropower Development Company Ltd.
Solar farm
Type
External links
Websitehttp://ridihydro.com.np/home/pagesDisp/butwal-solar-pv-project

Butwal Solar PV Project is located at Rupandehi District of Lumbini Province, Nepal. The plant is owned and run by Ridi Hydropower Development Company Ltd, an IPP. The plant came in operation in October 2020.[1]

The power station has capacity of 8.5 MW consisting of 32,640 number of solar panels - each generating about 330 watts peak power. The plant occupies an area of about 26 Bighas of land (approx. 17.2 hector).[2] The energy generated by the project is connected to the 33 kV Butwal Substation in Tilottama. The solar station generates energy only during the daytime.[3]

The plant was built in 10 months at the cost of NPR 65.5 crores.[3] The loan is financed by Bank of Kathmandu along with Citizens Bank and Nepal Bangladesh Bank.[4] The electricity is sold to Nepal Electricity Authority at rate of NPR 7.3/unit for 25 years.[2] After 25 years, the ownership will be transferred to the Nepal government.

Power Generation

Fiscal Year 2077/78[5] 2078/79[6] 79/80[7]
Shrawan - 1,044,060         1,210,340
Bhadra - 937,100        1,169,780
Aswin - 1,081,190         1,055,800
Kartik 568,510

(15 दिन)

1,082,440         1,193,230
mangsir 887,520 964,940         1,067,960
Paush 741,310 848,940             937,030
Magh 754,120 674,210             897,030
Falgun 1,032,770 1,336,600         1,275,090
Chaitra 1,210,070 1,260,660         1,413,720
Baishakh 1,225,630 1,248,750         1,327,540
Jestha 1,178,480 1,256,260         1,456,010
Asar 925,500 1,200,250         1,145,100
Total 8,526,910 9,873,050 14,148,630

See also

References

  1. ^ "Construction License :: Solar". Retrieved 2020-11-02.
  2. ^ a b "Butwal Solar Power Project (8.5 MW) Connected To National Transmission Line". Investopaper. Retrieved 2020-11-02.
  3. ^ a b "- Ridi Hydropower Development Company Limited". Archived from the original on 2020-11-05. Retrieved 2020-11-02.
  4. ^ Magazine, New Spolight. "BoK To Finance 8.5 MW Solar Plant In Butwal". SpotlightNepal. Retrieved 2020-11-02.
  5. ^ रिडी पावर कम्पनी लिमिटेड. "२०औँ वार्षिक प्रतिवेदन (आव २०७७/७८)" (PDF). रिडी पावर कम्पनी लिमिटेड.
  6. ^ रिडी पावर कम्पनी लिमिटेड. "२१औँ वार्षिक प्रतिवेदन (आव २०७८/०७९)" (PDF). रिडी पावर कम्पनी लिमिटेड.
  7. ^ Cite error: The named reference :0 was invoked but never defined (see the help page).